Renovation Timeline

timeline

Phase I renovation begins on 5/14 (expected duration: 3 months)

  • 5/14 – 6/1: Electrical, meetings rooms in upper fellowship hall, Classroom A (cry room)
  • 6/4 – 6/29: Sanctuary <– No sanctuary usage during this time
  • 7/2 – 8/10: Sanctuary renovation continued (Mezzanine level, rear wall, touch-up, etc) but space available for use, finish-up